Case Studies

Case Study 1

SITE - Delhi NCR (Amazon - DEL 5)

Total Area :

21 Acres

Built Up:

0.65 Million Sq Ft

Challenges Encountered

  • Project Delivery in 8 Months
  • Shortlisting of Land with Best Efficiency & Budget
  • Project Completion with All Legal Checks and Compliances
  • Construction in 6 Months
  • Fire Approval for one of the Largest Shed Structures as per NBC Norms
  • Shed Structure with Highest Specifications & Completely Air Conditioned
  • Unauthorized Structure Removal & Demolition

Value Addition

  • Cancellation of Multiple Deeds & Loans from Revenue Records, Negotiating the Deficiency in Physical Possession of Land leading to the Owner Fulfilling the Deficiency within the same Cost, As Per Market Rate, all Projects were executed at the Lowest Possible Rates
  • 45 Days (Land Acquisition)
  • 28 Days (CLU)
  • 65 Days (NHAI, Forest NOC, Aravalli NOC, Building Plan Approvals, Environment Clearance, Fire Scheme Approvals, Consent to Establish

Case Study 2

SITE - FARUKHNAGAR, Haryana - Flipkart

Total Area:

21 Acres

Built Up:

0.65 Million Sq Ft (0.45 Plinth & 0.20 Mezzanine)

Challenges Encountered

  • Local Villagers Interference & Consequent Delays
  • Imposition of NGT Ban
  • Water Declared unfit for Construction
  • Design Revision during Construction
  • Reduced Performance of Labour due to extreme Summer, Winter & Foggy Conditions
  • First Time Ever - Construction of Underground Fire Tunnel
  • Nationwide shortage of Cement Supply

Value Addition

  • Detailed Planning & Project Scheduling
  • Close Liason between Project Coordinator
  • Contractor & PMC Team
  • Timely Monitoring of Procurement Plan, Continuous communication with Local Villagers to resolve their Apparent Land Issues
  • Proper Logistics plan & purchase of Additional Water Tankers

Case Study 3

SITE - NH - 8 BINOLA, Haryana - Amazon

Total Area:

21 Acres

Built Up:

0.65 Million Sq Ft (0.45 Plinth & 0.20 Mezzanine)

Challenges Encountered

  • Project Continuosly on Critical path with No Slag
  • Multiple Vendors in Project
  • Multiple Scope Revisions
  • Design Revisions during Construction
  • Labour Management

Value Addition

  • Detailed Project Scheduling & Audit
  • Timely Monitoring of Procurement Plan
  • Employment of a Good Project Coordinator & Daily review with Stake Holders
  • Continuous communication with Amazon & Project Team
  • Parallel Activities
  • Hiring Labour Team on roll to Reduce Dependency on Labour Contractor